Progress at Weymouth Quay
04 January 2024
Since our last update in mid-December, the team at Knights Brown have made significant progress, despite breaking for Christmas. Possibly the most notable change is the demolision of Building F; a rather significant time for Weymouth Harbour as we see the last traces of the ferry terminal buildings disappear!
The slab for the fish bait store and fish landing stage are complete, and further progress has been made with drainage & ducting (compounds B&C). In the coming weeks, work towards the creation of the western and eastern ramps will take place, and more ducting (compounds A&B) and bases for the davit cranes will be installed.
More updates in a few weeks!